Unit 5, Ashchurch Business Centre, Tewkesbury, GL20 8TD
Project total – £
Landlord Enabling works to facilitate new letting, to include: structural repair to roof, overlaying of asbestos roof with new profile metal system, internal repairs, new LED lighting & panel heaters, and external repairs and decorations
Works carried out included:
- Full scaffolding
- Internal safety netting
- Over clad of the existing asbestos roof
- New LED lighting throughout, fire alarm installation and installation of panel heaters
- Replacement of existing front door with new UPVC door set
- Steelwork repairs and strengthening
Athena Avenue, Swindon, SN2 8EJ
Project total – £65k
Full refurbishment of this existing warehouse facility, comprising of a detached unit on its own self-contained site
The main warehouse area is arranged in two clear span portal frame bays, with an eaves height of approximately 8.42m
The warehouse is serviced with 8 dock level loading doors, and 3 surface level vehicle loading doors
There is a fully refurbished 2-storey office and stores area to the front of the property
Visitor parking is at the front of the building with two secure yards, one to the west of the building and one to the south of the building
Unit 10, Ashley Hill Trading Estate, St Werburgh’s, Bristol, BS2 9XS
Project total – £100k
The works comprised of replacement of existing asbestos sheet roof covering with composite metal, replacement of doors/windows and refurbishment of the internal areas. Including:
- Scaffolding works
- Demolition and strip out works
- Alteration of existing layout to incorporate new WC’s and shop area
- Electrical alterations and new installations
- Decoration works
- Carpentry works including new partitions, doors etc
- Paint spraying of external cladding
- Removal of asbestos roof and installation of new metal clad roof and new rooflights
- New floor coverings
- New warehouse epoxy floor coating system
- New kitchenette
Unit 5, Point 4 Industrial Estate, Avonmouth, BS11 8DF
Project total – £200k
Internal and external refurbishment works:
- Over roofing lighting and fire alarm installation
- Window and door replacement
- External and internal decoration and replacement of internal finishes
- Demolition of partition walls internally, plus other strip out works
- Miscellaneous repairs
Units 36-37 Ganton Way, Techno Trading Estate, Swindon, SN2 8ES
Project total – £130k
Techno Trading Estate provides a modern detached warehouse facility of portal frame construction with clad and glazed elevations. Works completed include:
- General repairs to the roof and replacement of rooflights, cleaning of rainwater goods and servicing/minor repairs to roller shutter doors
- Works to external areas include general maintenance to vegetation, removal of fencing and cleaning of external areas
- Internally comprised of removal of tenant installed partitions, fixtures and fittings etc, removal of low grade asbestos to the bitumen floor tiles and cleaning throughout
- All mechanical and electrical installations were tested, serviced and repaired as necessary
Unit 8A, Point 4 Industrial Estate, Avonmouth, BS11 8DF
Project total – £300k
Internal and external refurbishment works:
- Over roofing lighting and fire alarm installation
- Window and door replacement
- External and internal decoration and replacement of internal finishes
- Demolition of partition walls internally, plus other strip out works
- Miscellaneous repairs
Brinsea, 32-33 Buckingham Rd, WSM, BS24 9BG
Fit-out and refurbishment of accommodation in connection with Brinsea Products Limited’s proposed occupation
Works include alterations and extension of M&E services, and:
- Minor demolition works
- Carpentry works, incl building of offices in jumbo stud partition
- Electrical alterations and new installations
- Decoration works
Units 4 & 12 Ash, Kembrey Park, Swindon
Internal and external repairs and redecoration
Unit 4
The scope of work comprises the internal and external repair and refurbishment of this industrial unit. The works are required in order to bring the unit up to a suitable standard, ready for re-letting
Unit 12
The scope of work comprises the internal and external repair and refurbishment of this industrial unit. The previous occupier operated the premises as a vehicle repair workshop. Some of the machines were to be left in place, and the office accommodation at the front of the unit re-built
Works carried out to both units included the following:
- Roof works
- Repairs & cleaning works
- Minor demolitions
- Plumbing
- Electrical
- Decorations
- Carpentry
- Partitions and suspended ceilings
Unit 9 Avon Way, Trowbridge, BA14 8RP
Fit out of a new distribution warehouse
The works comprised of refurbishment and repairs to an existing warehouse unit to form a new Smiths News distribution warehouse, including:
- Construction of welfare, office and print rooms
- Removal of existing incoming supply and installation of new lower voltage supply
- New electric, lighting and data installations
- Repair works to the external parking and loading/delivery areas
- Roof repair works
- Asbestos removal works
- Installation of new delivery entrance and roller shutters
- Repair/replace dock levellers
Unit 12 The Maltings, Bath, BA1 3JL
Refurbishment of light industrial accommodation
The project comprises refurbishment of light industrial accommodation, known as Unit 12 The Malting’s Industrial Estate, Bath
- Scaffolding
- Strip-out and demolition of the former occupiers fit-out internally, including mezzanine
- External decoration
- Repairs and making good to the exterior
- AC, plumbing, mechanical and electrical works
- Brick repair works
Former Herman Miller, Chippenham
Project total – £1.3m
The property was a circa 7,000m2 industrial warehouse with original single storey ancillary accommodation located to the front side and an ancillary WC pod. Works completed included an external roof repair/replacement, elevation repair and redecoration, internal repair and redecoration works to the warehouse and the construction of a welfare block